School children sit on buses for hours as road closures and accidents cause traffic ‘madness’ in Sittingbourne and heading to Sheppey
05:00, 03 July 2024
updated: 13:01, 03 July 2024
Schoolchildren were stuck on a bus home for hours during traffic “madness” that brought drivers to a standstill.
Pupils returning to Leysdown from Westlands in Sittingbourne arrived home at 7.50pm on Monday, despite being picked up at 4.30pm.
It came after a crash on the A249 coincided with various road closures.
Network Rail shut the Kingsferry Bridge on Friday for eight days, one of two routes onto the Island.
Meanwhile a lane of the approach on the A249 is down to one lane due to works at the Grovehurst junction. Chestnut Street on the A2 at Key Street was also closed in both directions for utilities.
One Sittingbourne driver claimed it took him more than an hour to get from St Michael’s Road to the Esso garage on London Road – a journey which would usually take four minutes.
Another said that when he walked through East Street for a doctor’s appointment he could see the same cars that were waiting in traffic after his appointment – 45 minutes later.
A gymgoer said it took him 50 minutes to get from Teynham to the Swallows Leisure Centre in Sittingbourne town centre – normally a 20-minute journey.
And Sheppey commuters having to use rail replacement services during the closure of the Kingsferry Bridge were left at Sheerness station for three hours because buses were unable to get onto the Island.
Network Rail is carrying out the works to urgently replace the 40 steel ropes that lift the bridge for maritime traffic.
A spokesman said the repairs would avoid a “sudden” and “disruptive unplanned” closure over the winter.
But Tim Lambkin, managing director of Travel Masters, says the thinking behind the works, which clash with the Grovehurst roundabout redesign, have not been “joined up”.
His firm has been providing the rail replacement services, as well as operating its usual school buses, something he says has been a “struggle”.
He said: “Because of the numerous closures, including the single lane closure for the Grovehust works, all it takes is one accident for the roads to snarl up.
“Usually drivers would have another route to use through Iwade to get to the Island but because of the bridge works, this option is not there. It means there’s more traffic going through Bobbing which backs up into Sittingbourne past Key Street.
“We were lucky on Monday that four busloads of primary school children who were on a trip returned before rush hour.
“It was bad enough that secondary school kids were stuck on a bus for hours but the younger children would not have handled it.
“It has been a real struggle for us and if the bridge works had been pushed back until the A249 flyover was open there would be less of a problem.
“People say everyone should just leave 15 minutes early, however, the problem is we are running at a strict timetable as kids need to get to school on time.”
Traffic issues, Mr Lamkin added, have been part of daily life for 10-12 months since the Grovehurst works began.
The £38.1 million improvement project was due to finish by the end of the year, however, a range of problems – including “issues with trapping reptiles” – have seen this date pushed back to next June.
Meanwhile, managing director of Chalkwell, which runs services across Swale, Roland Eglinton predicted that his firm would face “enormous challenges” during the closure.
The company has seen similar journey times as Travel Masters which he says “comes with a cost”.
He said: “During the day the roads were working but come 4pm everything went south.
“It’s a consequence of too many schemes all taking place at the same time and there’s not much we can do about it.
“The issue is inconvenient to our customers, and it comes at a cost in terms of fuel and wages.
“The first night of closures is usually the worst but we will see if drivers begin to take alternative routes.”
Jackson Civil Engineering, which is delivering the scheme, was approached for comment.
A KCC spokesperson said: “We are aware Network Rail is undertaking urgent work to the Kingsferry Bridge.
“Our teams have been working closely with Network Rail and we note its bridge works have been planned to minimise the impact to pupils travelling to sit exams during the summer.
“It is not possible to remove the traffic management from the southbound A249 as part of KCC’s Grovehurst Road Improvement Scheme to coincide with closures of Kingsferry Bridge, as the project is at a stage where doing so would create a significant risk to road users.
“We recognise major works are disruptive and we will continue to work with partners to monitor the situation.”
A Network Rail spokesman said: “We know that the impact of the Kingsferry Bridge closure this week, as well as a crash and a broken down vehicle in the area on Monday night, meant that there were delays for motorists’ and bus passengers’ journeys.
“We’re grateful to people for their patience as we complete these urgent repairs. Making these essential repairs now avoids us having to put in place a sudden and much more disruptive unplanned closure over the winter.
“By doing the work in summer, the risk of Sheppey Crossing, as the alternative route to the island, closing due to high winds is also significantly reduced.”
Latest news
Features
Most popular
- 1
Lorry bursts into flames on roundabout approach
5 - 2
Greyhound track to close after 40 years
- 3
Man dies after being hit by lorry on motorway
21 - 4
Christmas light switch-on cancelled due to ‘safety concerns’ from bad weather
2 - 5
Rolexes and crypto: How dealer selling drugs from bedroom hid ‘massive profits’
18